Source: Asia Pacific Report
By Kaya Selby of RNZ Pacific
New Zealand will foot the bill for any cost blowouts the Cook Islands’ Penrhyn port upgrade, new details about the funding arrangement reveal.
That is despite Cabinet agreeing to greenlight the project with the caveat that Aotearoa’s contribution of US$10 million would be its “maximum”.
The project, announced at the Pacific Islands Forum leaders’ summit on September 1, is a joint proposal between the New Zealand, United States and Cook Islands governments to build a deep-sea port, extending a Second World War American-built air base.
The US and New Zealand governments will jointly fund the NZ$101 million project — the Americans contributing US$50 million (approximately NZ$84 million), while New Zealand will contribute NZ$17.5 million (approximately US$10 million).
In a decision from August 31 — a day before the announcement — it was agreed that the project would proceed, provided it passed a feasibility study, the Cook Islands continued to support it, and that it could happen “within the combined funding envelope approved by Cabinet”.
A Cabinet minute prepared by Foreign Minister Winston Peters’ office noted that the deal would proceed, “only if we have confidence that the funding available for the chosen project is sufficient to fully fund its implementation”.
But this also appeared to be the US approach, as the majority funder. According to the paper, its US$50 million contribution to the project is a “one-off fixed sum”.
“New Zealand would therefore be responsible for any cost increases; this is a standard risk for all development projects that New Zealand implements,” the Cabinet documents state.
This is despite the fact that the US is currently negotiating the extent to which a military presence, which is confirmed to include Coast Guard vessels, may be accommodated on the atoll.
Though it acknowledged construction would be “complex and expensive, given its remoteness and lack of supporting infrastructure, local materials or labour supply”, the unredacted contents made little mention of the prospect of a cost blowout.
It discussed the most likely benefits of the project, including that it supports New Zealand’s “long-term objective to see the US maintain its presence and standing in the Pacific”.
High-risk, high-reward
The project was born when the US approached New Zealand in April, offering an undisclosed sum of money and a commitment to a port upgrade.
The initial sense from the Ministry of Foreign Affairs and Trade (MFAT) advisers, according to April advice released under the Official Information Act (OIA), was that the project “will be possible, but it needs extensive further work”.
It noted a 2023 feasibility study by the Australian government — that New Zealand had no part in — but the final cost estimate was redacted.
“New cost estimates will need to be prepared to support the project, which are expected to be significantly higher.”
Advice from May also noted that New Zealand had saved money, enough for “a reasonably significant infrastructure investment”, because it had paused aid to the Cooks during its year-long diplomatic spat.
Officials said that New Zealand was working on a US-led timeline at that point, and that without a business case, it was taking on serious risks.
“Cabinet consideration of a major New Zealand development activity would ordinarily be supported by a detailed business case prepared over a numbers of years with firm cost estimates.”
As a result, the September announcement was an intention to partner, rather than a sure thing. The August Cabinet paper gave a plan to start construction in 2029 and finish in 2031.
‘Unusual times’
Development expert Terence Wood said it was possible that New Zealand was willing to take on the risk for the sake of maintaining influence in the Cook Islands.
“Given how common budget blowouts are in large infrastructure projects, if NZ really is responsible for all cost increases, it is taking a risk — one that it would ideally avoid,” he said.
“But these are unusual times. [New Zealand] desperately wants to keep the Cooks away from China’s sphere of influence and it will be very keen not to irritate the Americans.”
MFAT opened a tender on September 7 for the study, with an initial one-year contract of NZ$1.5 million, followed by further work of one to four years for NZ$3-6 million. That alone could make up about 43 percent of New Zealand’s overall contribution.
Wood said that, from a development perspective, it was not a good use of money.
“[But] from a geostrategic perspective, it’s pretty easy to see why the government is taking on the risk.”
This story was first published on
Original source: https://analysis1.mil-osi.com/2026/11/16/nz-to-cover-cost-blowouts-in-penrhyn-port-upgrade-cabinet-documents-reveal/